Located in China’s geographical center, adjacent to the Yellow River in the north, Mount Song in the west, and va...
MoreItem Name | Construction Land Planning Permit |
---|---|
Rights and Liablities Item No. | |
Issuing Authority | Zhengzhou Area of China(Henan) Pilot Free Trade Zone |
Service Subject | Legal person |
Implementing Basis | Urban and Rural Planning Law of the People's Republic of China Promulgation date: 28/10/2007Order of the President of the People's Republic of China (No. 74)
Article 37: If the right to use state-owned land for a construction project within a city or a town planning area is appropriated, upon the approval or verification of the related department, or putting- on-archive of the project, the construction entity shall apply to the component department of urban and rural planning under the government of the city or town for permitting the land use for construction, and the department shall issue a construction land use permit after checking and verifying the location and area of the land for construction as well as the scope of areas where construction is permitted in accordance with the regulatory detailed planning. The construction entity may only apply to the competent department of land under the local people's government at or above the county level for land use after obtaining the land use permit. The competent department of land may appropriate land to it upon the approval of the people's government at or above the county level. Article 38: If the right to use state-owned land within a city or town planning area is assigned, the competent department of urban and rural planning under the people's government of the city or county shall, before the assignment, raise such planning requirements as the location of the land to be assigned, nature of its use and development intensity as a component of the contract for assignment of the right to use start-owned land on the basis of regulatory detailed planning. As for any state-owned land, if the planning requirements are not specified yet, the right to use it may not be assigned. If the right to use state-owned land for a construction project is obtained by assignment, the construction entity shall, after concluding the contract for assignment of the right to use start-owned land, obtain the land use permit from the competent department of urban and rural planning of the people's government of the city or county upon the strength of the approval, or verification or archive-filing documents of the project as well as the contract for assignment of the right to use start-owned land. The competent department of urban and rural planning of the people's government of the city or county may not change the planning requirements which constitute a component of the contract for assignment of the right to use start-owned land in the land use permit without approval. |
Application Condition | Any construction project appropriated or assigned the right of state-owned land use within a city or a town planning area |
Application Materials | Materials required are as follows(copies are required to check the original and stamped with the construction unit seal and the signature of the construction unit manager): 1. Administrative licensing application; 2. The identity certificate of the legal representative or entrusted agent; The power of attorney of the entrusted agent; 3. Business License of Enterprise Legal Person or Organization Code Certificate; 4. Construction project site submissions; 5. Documents related to the approval, verification, and putting-on archive of the construction project; 6. Current topographic map. |
Transaction Procdure | Acceptance→checking→settlement |
Transaction Time Limit | 30 Working Days |
Implementing Authority | Zhengzhou Urban and Rural Planning Bureau |
Charge or not | No |
Fee Standard | None |
Fee Basis | |
Online Application or not | No |
Business Supervision Department | |
Office Hours | Mon. - Fri. 9: 00-12: 00 13: 00-17: 00 |
Office Address | The 1st and 2nd floor of Building 1, No. 85, Yabao Oriential International Plaza, Jinshui East Road, Zhengzhou.(Zip Code 450046) |
Contact Phone | 0371-67888391 |
Complaint Phone | 0371-67880110 |
Relevant Forms | |
Flow Chart | |
Common Questions | |
Notes |
Integrated Service Center of China (Henan) Pilot Free Trade Zone Zhengzhou Area Add.:1 Yabao·Dongfang International Plaza,No.85 Jinshui East Road,Zhengdong New District,Zhengzhou,Henan,China Tel.:+86 0371-61170000 0371-67880002 E-mail:zzszzq@126.com |